Construction of the new Ministry of Defence and Veteran Affairs (MoDVA) and Uganda Peoples’ Defence Forces (UPDF) headquarters in Mbuya, Kampala, has reached 87% completion, according to SoftPower News. The project is now expected to be commissioned in December 2026, marking a major step in the government’s effort to consolidate defence administration in one modern facility.

The publisher reported that Chief of Defence Forces Gen Muhoozi Kainerugaba visited the site and praised the UPDF Engineering Brigade for the progress achieved so far. The article indicates that the new headquarters will house both the ministry and the armed forces command, though the snippet does not provide additional details on the full scope of the building or the remaining work.

The development matters because it reflects ongoing investment in Uganda’s defence infrastructure and could improve coordination between the ministry and the military leadership. More broadly, headquarters projects of this kind are often intended to streamline operations, centralize offices and strengthen administrative efficiency, though those general benefits are background context rather than specifics confirmed in the report.

SoftPower News’s public article text on the page appears to reference a separate story about UPDF participation in the 2027 Invictus Games, so the construction update is based on the headline and source snippet provided.

Read the full report at SoftPower News →

Loading debate for this article…

Other publishers covering this story

No additional verified coverage is currently clustered with this report.

Related reporting